PT Vale's HPAL Sambalagi project reaches a key downstreaming milestone as its autoclave arrives in Morowali

By Sirkularium Editorial Team, 8 min read

Large industrial autoclave vessel being installed at a nickel HPAL processing plant construction site in Morowali, Central Sulawesi

The autoclave at the heart of PT Vale Indonesia's HPAL Sambalagi project arrived in Morowali on 22 July 2026, a milestone toward a facility designed to produce 90,000 tons of nickel content a year for the electric vehicle battery supply chain. Tailings design work now underway is the detail worth tracking as the project moves toward construction.

At a glance
90,000 t/year
Nickel content HPAL Sambalagi is designed to produce annually, as mixed hydroxide precipitate
10.4 million t/year
Limonite ore the plant will draw from PT Vale's Bahodopi mining area to supply that output
3 lines
Production lines (A, B, C) targeted for first mechanical completion by end of 2026
2 valleys
Valleys near Sambalagi being leveled and engineered for the project's tailings storage facility

What arrived in Morowali

On 22 July 2026, an autoclave, the core pressure vessel of a High Pressure Acid Leaching (HPAL) processing line, arrived at PT Bahodopi Nickel Smelting Indonesia's Sambalagi site in Bungku Pesisir, Morowali Regency, Central Sulawesi. ANTARA News, Liputan6, Telisik.id, Kendari News, and Tekape.co all reported the arrival on 23 July, describing it as the project's most significant construction milestone to date. The autoclave processes limonite ore through a combination of high temperature, high pressure, and sulfuric acid, extracting nickel and cobalt into a mixed hydroxide precipitate, or MHP, the intermediate product that feeds electric vehicle battery supply chains.

Bernardus Irmanto, President Director and CEO of PT Vale Indonesia Tbk, called the arrival a critical milestone. "Autoclave ini merupakan tonggak penting yang mendukung rantai pasok global kendaraan listrik," he said, meaning the autoclave marks an important step supporting the global electric vehicle supply chain. Minister of Investment and Downstream Processing and Head of BKPM Rosan Perkasa Roeslani, Central Sulawesi Deputy Governor Reny Arniwaty Lamadjido, and Morowali Regent Iksan Baharudin Abdul Rauf attended alongside company officials, underscoring the project's standing as a National Strategic Project, or PSN, designated under Coordinating Ministry for Economic Affairs Regulations No. 9 and No. 21 of 2022.

Bernardus Irmanto, President Director and CEO of PT Vale Indonesia: "Autoclave ini merupakan tonggak penting yang mendukung rantai pasok global kendaraan listrik."

The scale of what is being built

HPAL Sambalagi is designed to produce approximately 90,000 tons of contained nickel a year in MHP form, drawing on roughly 10.4 million tons of limonite ore annually from PT Vale's Bahodopi mining area. The facility is being developed by PT Bahodopi Nickel Smelting Indonesia, a joint venture between PT Vale Indonesia, China's GEM Co. Ltd., and South Korea's EcoPro, inside the Indonesia Green Industrial Park. Three production lines, labeled A, B, and C, are each targeted for first mechanical completion by the end of 2026.

The plant's design incorporates a Waste Heat Recovery Power Generation system that converts residual process heat into electricity, alongside planned solar power capacity for the wider industrial zone, features the companies present as core to the facility's low-carbon positioning relative to older nickel processing routes. Supporting infrastructure under construction includes a logistics dock, worker housing, and social facilities for the surrounding community.

The tailings question now entering design

HPAL technology produces substantially more waste by volume than the nickel it recovers, and Sambalagi's own construction schedule reflects how much engineering attention that waste stream now requires. Kontan's Jelajah Ekonomi desk, reporting from the site in June 2026, described plans to level two valleys near Sambalagi to house the project's tailings storage facility, the repository for residual material left after the HPAL extraction process. Khristya Pramitha, Bahodopi HPAL Project Engineer at Vale Indonesia, said the facility design remains in soil testing and technical review, with Vale conducting its own independent review of the designs prepared by BNSI management. Construction of the initial tailings area is targeted to begin in August 2026, with a partial facility expected operational by early 2027. The project's long-term plan is to eventually repurpose closed, filled tailings areas for solar panel installation, folding the waste footprint back into the site's renewable energy plans rather than leaving it as permanently idle land.

That design-stage caution sits against a national backdrop that gives it real weight. Energy Shift Institute (ESI), an independent research organization, published an analysis on 15 July 2026 projecting that Indonesia's stock of HPAL-derived nickel waste could reach 1.4 billion tons by 2035, roughly ten times current stored volumes, based on the output of HPAL facilities already operating, under construction, or planned nationally. ESI's analysis notes that HPAL tailings typically contain chromium at 1 to 1.5 percent by weight, and that Indonesia-wide chromium entering storage could reach an estimated 1.4 to 2.0 million tons a year by 2030, a figure ESI frames as the reason storage design and monitoring standards deserve as much attention as production capacity. The same analysis points to the tropical rainfall common across Indonesia's nickel regions, in the range of 2,400 to 3,000 millimeters annually, as a factor that specifically raises the engineering bar for slope and storage stability, which is precisely the kind of site-specific geotechnical work now under review at Sambalagi.

Why the economics of tailings design matter

ESI's analysis also makes an economic point worth foregrounding alongside the engineering one: stricter tailings storage standards raise upfront construction cost, but the same analysis notes that higher storage standards can make iron recovery from tailings more economically viable, turning a stored waste stream into a partially recoverable resource rather than a permanent liability. That reframing, treating tailings as an asset to be valued and potentially recovered rather than only a hazard to be contained, is consistent with how Indonesia's environmental economics regulations already price ecological damage and recovery cost under Permen LH No. 7 Tahun 2014, and it extends naturally to a facility still in its design phase, where the cost of building monitoring and recovery potential in from the start is lower than retrofitting it later.

What comes next

The next visible milestones at Sambalagi are the August 2026 start of tailings construction, the targeted first mechanical completion of the three production lines by the end of 2026, and the partial tailings facility coming online in early 2027 ahead of full plant commissioning. Each of those dates gives government agencies, financiers, and the communities around Bungku Pesisir a concrete point to check design assumptions against actual construction as it proceeds, rather than waiting until the plant is operating to ask whether the tailings facility performs as designed.

Sirkularium's view

Sirkularium reads the HPAL Sambalagi milestone as a genuine downstreaming achievement, and one where the project's own caution around tailings design is worth encouraging rather than treating as an afterthought. Vale's decision to run independent design reviews and phase tailings construction behind soil testing, rather than building to a fixed schedule regardless of ground conditions, is the right instinct for a facility sited in a high-rainfall region on Indonesia's nickel frontier.

What would strengthen that instinct further is an independently verified, GIS-based baseline survey of the two valleys now being engineered for tailings storage, covering slope stability, water table condition, and downstream watershed sensitivity, established before construction begins and repeated on a fixed schedule once the facility operates. That baseline would give PT Vale, its joint-venture partners, and the ministries overseeing the PSN designation a shared, quantified reference point for what responsible tailings management looks like at this specific site, not only against Indonesia's own regulatory standards but against the kind of long-horizon risk ESI's national projection is asking the sector to plan for now. For a project already moving quickly toward its 90,000-ton production target, building that valuation discipline in during the design phase is the more defensible foundation to scale from.

ShareLinkedInWhatsAppFacebookEmail
Sirkularium

Sirkularium is a thought-leadership and advisory institution accelerating the circular transition across solid waste, water, and energy, working with government and public institutions.

In sustainable resources, Sirkularium advises on water, tailings, and ESG governance so resource projects stay credible and investable.

Related articles

Aerial view of a revegetated former mine terrace in Indonesia, young trees in rows beside an active pit, as seen in satellite-style top-down framing
Sustainable Resources

The Directorate General of Minerals and Coal says reclamation guarantees placed by mining companies have grown from about Rp17 to 18 trillion to around Rp40 trillion, with satellite imagery used to size each deposit to the land actually opened. The Ministry of Environment adds that success will be judged on the ground, not on paper.

By Sirkularium Editorial Team, 8 min read

Aerial view of a nickel processing complex in Sulawesi with stockpiles of ore and a refinery block, or nickel matte and MHP product bags at a port
Sustainable Resources

Coordinating Minister Bahlil Lahadalia has opened the option of a moratorium on new nickel smelters that produce intermediate products such as NPI, ferronickel, nickel matte and MHP, citing a global surplus of about 2.5 million tonnes. The move reframes the next phase of downstreaming around how much value each tonne of ore retains in Indonesia.

By Sirkularium Editorial Team, 8 min read

Forested slopes of Mount Tompotika in Banggai Regency, Central Sulawesi, with farmland and a village in the foreground
Sustainable Resources

The Central Sulawesi Information Commission has ruled that the environmental approvals and AMDAL documents for PT Anugerah Bangun Mamur and PT Anugerah Sumber Bumi in Banggai Regency are public information, to be shared with the Tompotika Conservation Alliance within 14 working days. The decision turns the AMDAL into a shared baseline for valuing the forests, water, and endemic wildlife of the Tompotika landscape.

By Sirkularium Editorial Team, 8 min read

Amandit Weir in Malutu Village, Hulu Sungai Selatan, with clear water flowing over the spillway and forested Meratus foothills behind
Sustainable Resources

The regent of Hulu Sungai Selatan has proposed piping clear raw water from the Amandit Weir to the Muara Banta intake that serves Kandangan. A treatment plant built for Rp16.8 billion and running at 50 of its 300 litres per second shows how much value a better source can carry.

By Sirkularium Editorial Team, 8 min read

Indonesian and Chilean delegations at a bilateral meeting in Santiago, with copper cathodes or a modern tailings facility as an alternative industrial image
Sustainable Resources

In Santiago on 1 October 2026, Deputy Foreign Minister Arif Havas Oegroseno proposed an Indonesia-Chile Green Minerals Partnership MoU covering joint industrial projects, a producer-country coalition, green mining technology, investment platforms, and the management and reuse of tailings. Chile's Foreign Minister welcomed the proposal and pledged early follow-up.

By Sirkularium Editorial Team, 8 min read

Police officers inspecting passenger bus cargo at the Bakauheni ferry terminal in South Lampung, with sealed bottles of seized evidence on a table
Sustainable Resources

Routine screening at Bakauheni Ferry Port stopped 61 kilograms of undocumented mercury labelled for gold processing, and investigators traced the shipment to a recipient in Bogor. The case shows how interrupting mercury supply complements Indonesia's Minamata commitments, and why the avoided environmental loss deserves to be valued.

By Sirkularium Editorial Team, 8 min read