Bandung moves its refuse derived fuel up the value chain, from loose RDF to briquettes

By Sirkularium Editorial Team, 8 min read

Compressed refuse derived fuel briquettes stacked at an Indonesian integrated waste processing facility, with sorting conveyors and shredding equipment in the background

Bandung City Secretary Iskandar Zulkarnain inspected the Tegalega integrated waste processing facility on 5 August 2026 and set a higher product specification for it: not bulk refuse derived fuel, but pressed briquettes with a wider buyer base. The plant is designed for 25 tonnes of waste a day and was built for Rp19.9 billion under a World Bank supported programme.

At a glance
25
Tonnes a day TPST Tegalega is designed to process
Rp19.9 billion
Construction cost of TPST Tegalega
60
Tonnes a day of combined capacity at TPST Cicukang Holis
600
Tonnes a day, Bandung's stepped disposal quota to TPA Sarimukti

On Wednesday, 5 August 2026, Iskandar Zulkarnain, Regional Secretary of Bandung City, walked the Tegalega integrated waste processing site and came away with a revised instruction for the plant. It should not stop at producing loose refuse derived fuel. It should press that material into briquettes.

The change reads as a technical detail. In commercial terms it is the difference between a single off-take relationship and a product with several possible buyers. Republika Rejabar reported the inspection on 6 August, with Kapol.id, Koran Jakarta, Tribun Jabar and Radar Bandung covering the same visit. The consistency across those accounts is useful, because it means the city has been explicit in public about what it wants the facility to deliver.

Kalau produk akhirnya sudah berbentuk briket, nilai ekonominya tentu lebih menjanjikan. Briket ini bisa diterima oleh beberapa off-taker dan bahkan dapat dimanfaatkan sebagai bahan bakar untuk jenis kompor tertentu yang digunakan pelaku UMKM.

Zulkarnain's point, rendered plainly, is that a briquette carries a better economic proposition than bulk RDF, that several off-takers will accept it, and that it can serve as fuel for certain stove types used by small and micro enterprises. That last clause is the interesting one. It puts a municipal waste product into a domestic energy market rather than leaving it dependent on a single industrial buyer.

What the facility was built to do

TPST Tegalega is not a new asset. According to the Ministry of Public Works, construction ran from 13 July 2023 to 2 December 2024 at a cost of Rp19.9 billion, financed through the World Bank supported Improvement of Solid Waste Management to Support Regional and Metropolitan Cities programme, with the West Java Building, Infrastructure and Area Development Agency acting as operator. Deputy Minister of Public Works Diana Kusumastuti inspected it alongside TPST Cicukang Holis in June 2025.

Its original purpose was straightforward. ANTARA News Jawa Barat reported in January 2025, when the plant was completing its testing phase, that it was designed to turn 22 to 25 tonnes of waste a day into refuse derived fuel for the cement industry. A Koswara, then Acting Mayor of Bandung, noted at the time that the feedstock was not household waste in the raw sense but material recovered from transfer station sorting and from city parks: residue, leaves, branches and organic matter.

Koswara also flagged the constraint that still shapes the plant's economics today. When waste arrives unsorted, it has to be sorted again at the transfer station before it reaches the TPST, which doubles the handling work. Feedstock quality determines throughput. That is why the 25 tonne figure is consistently described as a target conditional on sorting discipline rather than a guaranteed daily rate.

The processing network Tegalega belongs to

Tegalega is one node in a deliberately decentralised system. The Ministry of Public Works records TPST Cicukang Holis at 60 tonnes a day of combined capacity, split between a 10 tonne first phase built between 12 December 2024 and 25 May 2025 for Rp5.8 billion, and a 50 tonne second phase built between 13 July 2023 and 25 April 2025 for Rp41.2 billion. Both were financed under the same World Bank programme.

Set against the city's overall load, these are modest units, and they are meant to be. Reported daily waste generation for Bandung varies across sources, from more than 1,200 tonnes in some accounts to about 1,500 tonnes in others and 1,700 tonnes in Kompas Bandung's June 2026 reporting. Sirkularium notes the range rather than settling on one figure, since the numbers appear to reflect different measurement bases and different periods. What the accounts agree on is direction: volumes have been rising.

Alongside the engineered plants, Bandung has been building capacity at the neighbourhood level. Teropong Media reported in May 2026 that the city had 1,510 composting pits in place with a combined capacity above 2,800 cubic metres, against a target of 25,000 across all community units, together with 18 operating processing units handling roughly 18 tonnes a day and two further units using additional processing technology awaiting operation.

Why the timing matters

Bandung is working to a schedule. The city's disposal quota to TPA Sarimukti has been stepped down in stages, moving from 980 tonnes a day toward 600 tonnes, with reductions applied at roughly two week intervals. Kompas Bandung reported in June 2026 that Sarimukti's remaining capacity was projected to be reached in October 2026, while the regional replacement at Legok Nangka in Nagreg is planned to begin operating in 2029.

That gap between one site reaching its limit and its successor coming online is the practical reason the Tegalega decision matters now. Every tonne processed into a saleable product is a tonne that does not need disposal capacity. Mayor Muhammad Farhan has framed the response in terms of local solutions, particularly for organic material, rather than continued reliance on transfer stations alone.

Read that way, the briquette instruction is not a refinement for its own sake. It is an attempt to make the processing route financially self supporting during the period when the city most needs it to run at capacity. Bulk RDF sold into cement kilns is a real market, and the city has been clear it will continue supplying bulk material under existing industrial arrangements. Adding a briquette line widens the customer base without abandoning the original one.

Commissioning before handover

The city has also been deliberate about acceptance. Zulkarnain stated that the equipment was procured by the Ministry of Public Works and will be granted to the regional government, but that the city will accept the assets only once all functions are genuinely optimal.

Commissioning is underway, and the evaluation so far has identified equipment that needs refinement, with some units possibly requiring replacement because the machine specifications do not yet fully match the characteristics of Bandung's waste. Saying so publicly is a form of asset governance. A plant handed over before it performs becomes an operating cost for the receiving government, and the record of Indonesian waste infrastructure includes facilities that transferred in that condition.

Sirkularium's view

For government and public institutions, Tegalega offers three transferable lessons.

The first concerns product strategy. Public waste facilities are usually specified around throughput, measured in tonnes processed. Bandung is specifying around output value instead, asking what form the product should take to reach the widest set of buyers. Briquettes serving both industrial off-takers and micro enterprise stoves illustrate the difference between a plant that disposes of material and one that sells it.

The second concerns feedstock. Both the January 2025 and August 2026 accounts identify sorting quality as the binding constraint on capacity. Capital investment in processing equipment delivers its designed return only when upstream separation is working. For any local government financing a TPST, the household and transfer station sorting programme is part of the plant's business case, not a separate initiative.

The third concerns handover discipline. Conditioning acceptance on demonstrated performance protects the receiving budget and creates the right incentive during commissioning. It is a simple contractual posture that other regional governments receiving centrally procured assets can adopt directly.

What to watch next is whether the briquette specification converts into signed off-take. The economic case rests on buyers, and the named opportunity in the micro enterprise fuel market will need a price point, a distribution route and a consistent product standard before it becomes revenue. If Bandung can demonstrate that a 25 tonne a day municipal facility can sell into more than one market, the model becomes replicable at a scale most Indonesian cities can actually finance.

Daily design capacity of Bandung's World Bank funded TPST units

Values in tonnes per day

ShareLinkedInWhatsAppFacebookEmail
Sirkularium

Sirkularium is a thought-leadership and advisory institution accelerating the circular transition across solid waste, water, and energy, working with government and public institutions.

In waste and pollution, Sirkularium helps design collection, sorting, and recovery systems, draft policy and roadmaps, and turn waste into a managed resource.

Related articles

A licensed waste haulage truck being checked by city environment officers at a transfer point in North Jakarta, with sorted material and municipal signage visible
Waste & Pollution

On 13 August 2026 the Jakarta Environment Agency issued administrative sanctions against four licensed waste haulage companies that delivered material to an unofficial collection point in Cilincing instead of TPST Bantargebang. It is the third enforcement round in a fortnight, and it closes the last open link in the city's shift from collect and dump to sort, transport and process.

By Sirkularium Editorial Team, 9 min read

Workers checking sorted and baled plastic material on a conveyor line inside an Indonesian plastic recycling plant
Waste & Pollution

At the ASEAN Recycling Summit on 12 August 2026 in Jakarta, ADUPI, IDCTA and ESGIN signed a memorandum of understanding to build digital traceability and verified reporting across the plastic recycling chain. The work points directly at the national target of 100 percent managed waste by 2029.

By Sirkularium Editorial Team, 9 min read

Regional government leaders and company executives at a formal cooperation agreement signing in a Javanese government hall, with a rendering of a waste to energy facility displayed behind them
Waste & Pollution

On 11 August 2026 the Special Region of Yogyakarta, Sleman, Bantul and the city of Yogyakarta signed a cooperation agreement with Danantara for the PSEL waste to energy facility at Piyungan. The plant carries an estimated Rp2.5 to 3 trillion investment, will process 1,000 tonnes of waste a day, and is targeted for groundbreaking in December 2026.

By Sirkularium Editorial Team, 9 min read

Waste sorting workers in high visibility vests and gloves working a sorting line at an Indonesian recovered fuel plant, with baled material and conveyor equipment behind them
Waste & Pollution

On 10 August 2026 the Ministry of Environment, the Ministry of Manpower and the Jakarta provincial government launched social protection for the informal waste sector at the Rorotan recovered fuel plant in North Jakarta. Work accident and death benefit premiums fall by half to Rp8,400 a month, and the government is moving to reclassify the job itself.

By Sirkularium Editorial Team, 9 min read

An integrated waste processing facility under construction in Mataram, West Nusa Tenggara, showing a large sorting hangar, conveyor lines and stacked bales of recovered fuel material
Waste & Pollution

Public Works Minister Dody Hanggodo reviewed the TPST Kebon Talo project in Mataram on 9 August 2026. The Rp97 billion facility, due for completion on 31 December 2026, will sort 60 tonnes of waste a day on a 1.48 hectare site and convert the combustible fraction into solid recovered fuel.

By Sirkularium Editorial Team, 9 min read

Officials and army officers at a signing ceremony for a waste management partnership, with a landfill pyrolysis facility visible in an accompanying display
Waste & Pollution

On 7 August 2026 the Indonesian Army signed a joint commitment with the city governments of Bekasi, Bogor and Semarang and the Bogor regency government to build pre treatment and pyrolysis facilities at landfill sites. The plan gives the accumulated waste already sitting in landfills, rather than only the daily inflow, a defined route into an energy product.

By Sirkularium Editorial Team, 9 min read