PLN's biomass unit pushes fuel standards to scale coal-plant co-firing nationwide

By Sirkularium Editorial Team, 9 min read

Sawdust and woodchip biomass pellets being loaded onto a conveyor at an Indonesian coal power plant co-firing facility, with cooling towers visible in the background

PLN Energi Primer Indonesia says fuel quality standardization and supply chain efficiency, not feedstock scarcity, are now the binding constraint on expanding biomass co-firing across 52 coal power plants, as the company works toward a 2026 target of 3.65 million tons.

At a glance
52 plants
Coal power stations (PLTU) now running biomass co-firing, totaling 18,154 MW
2.35M tons
Biomass supplied to PLN's fleet in 2025
3.65M tons
Biomass supply target for 2026, rising to 4.07 million tons in 2027
2.72M tons
CO2-equivalent emissions avoided through co-firing in 2025

What happened

PT PLN Energi Primer Indonesia (PLN EPI), the fuel supply arm of state utility PLN, used a Material Handling Innovation for Wood-Based Industries symposium in late July to make a pointed argument: Indonesia's push to co-fire coal power plants with biomass no longer hinges mainly on how much agricultural and forestry residue the country can produce. It hinges on whether that residue can be collected, graded, and delivered to specification, at scale, on a schedule power plants can plan around.

Hokkop Situngkir, PLN EPI's Director of Biomass, told the symposium that the success of the co-firing program is determined by supply chain efficiency, fuel quality standardization, and reliable processing infrastructure, rather than by the underlying volume of biomass available nationally. It is a notable reframing. Indonesia's biomass resource base is large by any measure; Situngkir has separately cited a national potential of 83.4 million tons a year, concentrated in Sumatra (42.8 million tons) and Kalimantan (18.9 million tons). The binding constraint, in PLN EPI's own account, sits downstream of the raw resource, in logistics and quality control.

That framing matters because co-firing is one of the few decarbonization levers Indonesia can pull without idling existing coal assets. Roughly 90 percent of the country's installed generation capacity still runs on fossil fuel, spread across some 200 coal-fired units at 52 locations, another 200 gas and combined-cycle units, and close to 800 diesel units, according to figures Situngkir presented. Retiring that fleet outright is neither fast nor cheap. Blending biomass into the fuel mix lets plants cut their coal share and their emissions intensity while continuing to generate, which is why PLN EPI has made supply chain engineering, not just feedstock sourcing, the center of its 2026 strategy.

The numbers behind it

PLN EPI supplied 2.35 million tons of biomass to its co-firing fleet in 2025, which the company says avoided 2.72 million tons of carbon dioxide equivalent emissions over the year. Separate reporting on the program's implementation status put biomass utilization at 932,906 tons across the 52 participating plants as of June 2026, sourced from 16 distinct feedstock types with an average calorific value of 3,263 kilocalories per kilogram, indicators of the quality tracking now built into the program.

Cumulative supply across 2023 to 2026 stands at 4.77 million tons, dominated by two feedstock categories: sawdust at 54.6 percent and woodchips at 22.4 percent. PLN EPI's forward targets step up materially from here, to 3.65 million tons in 2026 and 4.07 million tons in 2027, with a longer-range ambition of reaching 10 million tons by 2030. Meeting the near-term targets alone would require roughly 9 million tons of biomass supply capacity feeding into the 52-plant, 18,154 megawatt co-firing fleet, a scale-up that explains why standardization, rather than headline feedstock potential, has become the company's stated priority.

To de-risk that scale-up for suppliers, PLN EPI has introduced purchase contract schemes running up to five years, giving farmers, cooperatives, and biomass processors the revenue certainty needed to invest in collection and processing infrastructure rather than selling into a spot market. The company frames this explicitly as ecosystem-building rather than simple procurement.

"Bioenergi bukan hanya mengganti batu bara. Yang kami bangun adalah ekosistem bioenergi dari desa hingga pembangkit listrik," Situngkir said, describing the program as bioenergy that does more than substitute for coal, built as an ecosystem stretching from villages to power plants.

Feedstock sources named by PLN EPI include palm empty fruit bunches, palm shells, rice husks, corn cobs, palm fronds, and wood waste, all residues drawn from forestry, plantation, and agricultural operations rather than purpose-grown biomass, a distinction the company has emphasized to preempt land-use and deforestation concerns.

Why it matters

Indonesia's energy transition debate tends to center on new-build renewables, solar, wind, and storage, where the country still trails regional peers on installed capacity. Co-firing is a different kind of lever: it improves the emissions profile of assets that already exist and are already paid for, without waiting on new transmission or permitting cycles. For an economy where coal still anchors around 90 percent of generation, that makes co-firing one of the more immediately deployable decarbonization tools available to policymakers and to PLN itself.

The standardization push also has a regional development dimension that is easy to overlook in aggregate emissions figures. PLN EPI has been building physical collection infrastructure to match its sourcing ambitions, including biomass hub facilities in Tasikmalaya and Ciamis in West Java designed to aggregate and pre-process residue from surrounding farms before it reaches power plants. The company's broader biomass ecosystem plan, tied to a 2025 to 2029 new-and-renewable-energy target of 12.22 gigawatts, projects roughly Rp 1.682 trillion in associated investment and around 760,000 green jobs across the supply chain, from smallholder collection through processing and logistics.

That employment and investment case is precisely why PLN EPI has chosen to lead its public messaging with supply chain quality rather than with tonnage targets alone. A biomass program that cannot guarantee consistent fuel specification to power plant operators will struggle to hold its purchase contracts, however generous the residue potential looks on a map. Standardization is what converts a resource estimate into a bankable, repeatable industrial input.

What comes next

The next test for the program is execution against its own numbers: whether 2026 supply reaches the stated 3.65 million ton target, whether the five-year purchase contracts attract enough farmer and cooperative participation to build durable collection networks, and whether the Tasikmalaya and Ciamis hub model is replicated at the pace needed to support 52 plants simultaneously. PLN EPI has signaled it intends to keep expanding hub infrastructure through the remainder of the decade as co-firing volumes climb toward the 10 million ton mark targeted for 2030.

Sirkularium's view

For government and public institutions, the PLN EPI case is a useful illustration of a broader principle in Indonesia's circular economy transition: resource abundance and program success are not the same thing. The country's biomass potential is not in question. What has determined whether that potential converts into avoided emissions is quality standardization, contract structures that give suppliers planning certainty, and logistics infrastructure built ahead of demand rather than in response to it.

Institutions overseeing co-firing policy, industrial decarbonization roadmaps, or regional biomass economic development programs should treat supply chain standards, not just feedstock inventories, as the metric worth tracking closely. Standardized fuel quality specifications, transparent calorific value reporting, and multi-year offtake certainty are replicable across other biomass value chains beyond power generation, including industrial boilers and cement kiln co-processing, sectors also named in Indonesia's industrial decarbonization roadmap. Financing and technical assistance aimed at collection and pre-processing infrastructure, rather than at plantation-level supply alone, is likely to have the largest marginal effect on how quickly national co-firing targets are met.

PLN EPI biomass supply, actual and targeted

Values in million tons

ShareLinkedInWhatsAppFacebookEmail
Sirkularium

Sirkularium is a thought-leadership and advisory institution accelerating the circular transition across solid waste, water, and energy, working with government and public institutions.

In energy and climate, Sirkularium supports emissions baselines, renewable and storage planning, and carbon and policy frameworks that hold up in practice.

Related articles

A sorghum field in Lampung beside a pilot scale bioethanol processing unit, with technicians in safety gear inspecting fermentation and distillation equipment
Energy & Climate

Pertamina New & Renewable Energy launched a Bioethanol Development Center in Tegineneng, Pesawaran Regency, Lampung on 14 September 2026, paired with a provincial cooperation agreement and an international research memorandum. The pilot plant is deliberately small at 60 kilolitres a year, built to prove feedstock, process and yield before capital commits at scale.

By Sirkularium Editorial Team, 9 min read

PLN technicians repairing a damaged electrical substation and transmission poles in a rural East Nusa Tenggara landscape shortly after an earthquake, with a national flag visible in the background ahead of Independence Day
Energy & Climate

A magnitude 7.0 to 7.7 earthquake struck the Flores Sea on 15 August 2026, knocking out two gas plants and damaging eleven substations in East Nusa Tenggara. PLN restored all eleven within 12 hours, then used the same province as its command post for the national grid's 81st Independence Day watch on 17 August, which closed with a 9 gigawatt, 21.1 percent reserve margin and no reported disruption.

By Sirkularium Editorial Team, 9 min read

Refinery workers and an operations manager reviewing a digital energy monitoring dashboard on a control room screen inside an Indonesian oil refinery
Energy & Climate

On 13 August 2026, PT Kilang Pertamina Internasional kicked off Bulan Energy & Loss 2026 simultaneously across all its refinery units, urging workers toward energy efficiency and loss reduction under a digitalization theme. The campaign follows a 2025 in which the refining unit cut more than 450,000 tonnes of CO2 equivalent against a 370,000 tonne target.

By Sirkularium Editorial Team, 8 min read

Interior of an Indonesian cement plant showing a rotary kiln and alternative fuel feed conveyor, with an operator in safety gear checking instrumentation
Energy & Climate

SIG reported on 13 August that alternative fuel use rose 24 percent to 681 thousand tonnes in 2025, displacing 467 thousand tonnes of coal and lifting its thermal substitution rate to 9.77 percent. Scope 1 emission intensity now sits 21 percent below the 2010 baseline, against a company target of 27 percent by 2030.

By Sirkularium Editorial Team, 8 min read

Provincial officials and community forestry group members signing documents at a table in a Jakarta meeting room, with Indonesian forest landscape imagery on a screen behind them
Energy & Climate

On 12 August the Environmental Fund Management Agency signed cooperation agreements with ten more provinces under the Results-Based Payment REDD+ Green Climate Fund programme, taking provincial coverage to 34 of 38. Total commitments to provincial programmes now stand at Rp761.02 billion, and the money traces back to 20.25 million tonnes of verified emission reductions.

By Sirkularium Editorial Team, 8 min read

Engineers and officials reviewing solar project plans on a table with laptops in a bright Jakarta meeting room, with a rooftop solar array visible through the window
Energy & Climate

At a media briefing in Jakarta on 11 August, Bappenas, GIZ and the Indonesian Solar Energy Association set out how ISEW 2026 will connect prepared projects with investors. The emphasis has shifted from headline capacity to bankability, grid readiness and a phased build sequence.

By Sirkularium Editorial Team, 8 min read